VSBA Schools Bundle
Name: VSBA Schools Bundle
Client: Hutchinson Builders
Location: Western Growth Corridor
Build time: 6 Months
This project consisted of the manufacture and installation of Glulam rafters across 6 schools as part of the Victorian School Building Authority’s 2023 Bundle A projects.
With a total of 22 education buildings completed, the Standstruct team excelled in fast-paced installation, setting a record of 56 rafters installed in 1 day.
Standstruct worked closely with our manufacturing partners to provide all aspects of manufacturing from shop drawing and review through to manufacturing and onsite installation.
FAST FACTS
Construction:
- 22 buildings completed
- 2,320 glulam rafters
- 117,076 bolts and screws
- 1,709 custom steel brackets
- 1,332lm of speed brace