Decjuba
Name: Decjuba
Client: Figurehead Constructions
Location: Cremorne
Build time: 3 Months
Standstruct was engaged by Figurehead Constructions to install this 4-level CLT and Masslam structure.
In a unique design for timber, each level consisted of a CLT floor plate, with a concrete slab installed on top, very similar to our Northumberland project for Grocon a few years back. This resulted in a visually stunning mix of the exposed blonde soffit of the CLT and a polished concrete floor.
Standstruct worked flawlessly with the incumbent structural concrete contractor to enable efficient floor completion time frames. Each CLT functioned as a permanent formwork, with each floor plate installed on a traditional concrete formwork. Once secondary steel-reinforced concrete had been installed, the formwork tables were removed and the CLT remained.
Standstruct also took on the install of all acoustic insulation and taping required in the CLT/concrete connection.
FAST FACTS
Construction:
- 175 CLT panels
- 2,142.9m² of CLT
- 14,847 screws
- 47 Masslam columns and beams
Transportation/Craneage:
- 11 small truck deliveries to allow for tight site access
- Onsite tower crane