Factory of The Future – Tonsley
Name: Flinders Uni Factory of the future
Client: Sarah Constructions
Location: Tonsley, South Australia
Build time: 2 Months
Standstruct Travelled to Tonsley, just south of Adeliade for this project for Sarah Constructions.
This Masslam post and beam construction was the first major project to use NexTimber CLT from their new Tarpeena manufacturing plant.
This project featured exposed CLT ceilings, 9 24m long Masslam trusses that were shipped to site in 2 parts then assembled by our crew onsite.
FAST FACTS:
- Construction:
-
- 37652 Screws and connections
- 4025m2 of CLT
- 162 Masslam Beams
- 118 Masslam Columns
- 9 24m long Masslam Trusses
- 179 individual NexTimber CLT Panels
- Transportation/Craneage
- 38 Semi loads of Timber
- 230t Slew Crane