Name: PHS Pod install

Client: Sinjen Group/Peninsula Hot Springs (PHS)  

Location: Mornington Peninsula, Victoria 

Build time: 2 Weeks

Standstruct was engaged by Sinjen Group and Peninsula Hot Springs for the recovery and install of QTY. 14 Prefabricated Pods to make up 10 new Eco Lodges.

Standstruct prepared these pods for transport, managed and assisted loading onto transport in the manufacturer’s facility in Geelong.

Utilising our partners Advanced Cranes and Rigging and their 650t crane, Standstruct installed the pods successfully with minimal impact to the surrounding Hot Springs Accommodation, in less than 2 weeks.

Standstruct also assisted Sinjen Group with general carpentry to round out the install.